New Tasks
In this section user must select one of the tasks listed.
Task definition actually is a step of work on each item. All activities which must be done for an item from start to end of the project, can be split into several tasks(Steps), each of which have its weight factor and totally 100.
When a step (task) is done for an item, related weight factor can be calculated as progress of that item. So sum of this weight factors when a those task(steps) will be completed is the total progress of Item.
And for the project, a simple formula can be used to calculate the Progress of the Project, like the below:
Total Progress of Items = |
∑ Progress of Items |
∑ Number of Items |